Settlement Monitoring for Embankment Dams in the UAE: Which Instrument, and When?

Home –  Blog

Why settlement matters

Every embankment settles. What matters is how much, where, and whether the design can tolerate it. On UAE water storage and flood protection embankments, often built on sabkha, uneven settlement can:

  • reduce freeboard at the crest
  • tear or overstretch the reservoir liner
  • open joints in outlet conduits, a classic path for internal erosion
  • crack the fill around rigid cut-off walls

First, decide when you need to measure

Most settlement happens while the fill is placed and in the first year after. On a 30 m high embankment, construction settlement can reach hundreds of millimetres, while later settlement is often only tens of millimetres. These need different instruments, so ask the designer for the predicted settlement at each stage before choosing.

The main instrumentation options

Rod extensometers and borehole liquid systems give settlement with depth; plate cells must go in during filling; survey monuments give the absolute crest movement.

Embankment dam cross-section showing rod extensometer, borehole liquid settlement system, plate cells, survey monuments and logger positions

Method

How it works

Typical accuracy

Best for

Liquid settlement, plate cells

Cells laid in the fill read a sealed liquid column to a reservoir on stable ground

±0.1% of range

New embankments, installed during filling

Liquid settlement, borehole type

Sensor grouted in rock; reservoir on a plate at the surface

±0.1% of range (about ±35 mm on 35 m)

Large movements; self-contained in one borehole

VW borehole rod extensometer

Anchors at several depths, rods to a head at the surface

Better than 0.1 mm

Completed embankments with small movements

Magnetic extensometer

Magnets on an access pipe, located with a probe

About ±1–2 mm

Large construction settlement; read manually

Survey monuments or robotic total station

Crest and slope points surveyed against off-site benchmarks

About ±1–3 mm

Absolute and differential settlement

The liquid in hydrostatic systems is a sealed water–glycol mix. It never carries reservoir water or groundwater.

Getting it right

  • Match accuracy to the movement. A 35 m liquid sensor reads to about ±35 mm: fine for construction settlement, too coarse for a 20 mm post-construction trend.
  • Anchor the deepest point in rock, or survey the head. Otherwise readings are relative, not absolute.
  • Watch differential settlement. Two boreholes far apart will not show it. Add survey points near conduits, cut-off walls and abutments.
  • Set trigger levels from the design predictions, for example alert at 80% and alarm above 100–120% of predicted, or when the settlement rate stops falling.

UAE site tips

  • Keep loggers and gateways above flood level. Radio does not work underwater.
  • Route cables to high ground, never through the liner or cut-off wall.
  • A LoRa network with one 4G gateway often beats a GSM modem at every logger.
  • Shade enclosures from direct sun and fit surge protection.

How CGT can help

CGT Engineering Consultant and Delma Laboratory review instrumentation specifications, compare instruments and suppliers, supervise installation and interpret monitoring data. Planning an embankment or water storage project? Contact us at info@cgteng.com before the instrumentation is specified.

Frequently Asked Questions

Can instruments be added to a finished embankment?

Yes. Rod extensometers, borehole liquid systems and survey points can be installed from the crest, but only measure settlement from then on.

Can readings be monitored remotely?

Yes. Vibrating wire instruments connect to loggers that send data over 4G or LoRa, with automatic alarms.

How often should settlement be read?

Weekly to fortnightly during construction, monthly in the first year, then quarterly or six-monthly, and after any flood or unusual seepage.